Emscher sewer tunnel - pipe factory Gelsenkirchen, Germany

Tilting table and lifting beam for concrete pipe segments

The hydraulic tilting table for tilting concrete pipe segments was developed for the pipe factory of the company Wayss & Freytag, located in Gelsenkirchen, Germany

  • load capacity: max. 40 t
  • length: 8,700 mm
  • width: 3,800 mm
  • height: 6,500 mm
  • deadweight: 27 t
  • tilting range: 90°
  • tilting time: 2 min.
  • lengths of pipe segments: 1,500 - 4,000 mm
  • including control panel

The concrete pipes are transferred to the tilting table in a standing position. After beiing tilted, the pipe can be removed by the hydraulic lifting beam off the table. Also the tilting of pipes from a laying position into a standing position is possible. The handling and monitoring of the tilting table is done by the integrated control panel.

The hydraulic lifting beam enables an innovative and safe handling of concrete pipe segments.
  • load capacity: max. 40 t
  • length: 5,700 mm
  • width: 800 mm
  • height: 6,200 mm
  • deadweight: 7 t
  • suspension brackets: 2
  • lengths of pipe segments: 1,500 - 4,000 mm

Go back